Skip to content

Get all the financial metrics for your construction company

You’ll know how much revenue, margin, and profit you’ll make each month without having to do any calculations.

Construction Company: Monthly Project Requirements

This article was written by our expert who is surveying the industry and constantly updating the business plan for a construction company.

construction company profitability

This briefing gives you a precise monthly checklist to run a construction company in October 2025.

It focuses on twelve operational questions that owners actually ask: project count, budgets, materials, workforce, subcontractors, equipment, safety, supply chain, cash flow, milestones, reporting, and risks. Numbers below reflect a practical scenario for a small-to-mid contractor managing five live jobs this month.

If you want to dig deeper and learn more, you can download our business plan for a construction company. Also, before launching, get all the profit, revenue, and cost breakdowns you need for complete clarity with our construction company financial forecast.

Summary

In October 2025, this model construction company runs 5 concurrent projects with a total working budget of $4.85M, tightly scheduled deliveries, and clear labor and equipment plans. Cash needs peak mid-month due to supplier draws and subcontractor progress payments.

Use the table below as your one-page control panel. Update quantities, dates, and rates weekly to keep decisions fact-based and on time.

Item October 2025 Status Operational Detail (who/what/when)
Active Projects 5 jobs (A–E) A: Retail fit-out; B: 12-unit residential; C: Warehouse shell; D: Roadworks (2.1 km); E: Villa renovation
Total Budget (Oct) $4.85M working budget A $0.65M; B $1.80M; C $1.60M; D $0.60M; E $0.20M (ex-VAT), with 10% contingency held centrally
Materials Major drops Weeks 2–3 Concrete 1,720 m³; rebar 165 t; CMU 42k units; asphalt 1,150 t; drywall 7,500 m²; finishes staggered Wk 3–4
Workforce Average 118 workers/day Carpenters 34; Masons 26; Steel fixers 14; Electricians 12; Plumbers 10; Operators 8; HSE 3; Site eng. 6; PMs 5
Subcontractors 12 active (9 confirmed, 3 pending) Pending: asphalt paving (D), glazing (B), HVAC (C) — award by Oct 6 to protect schedule
Equipment 7 key units on hire 1 x 50-t crane (C, 12 days); 2 x excavators (D, 10 days total); 3 x pumps (B/C, 9 days); 1 x paver (D, 4 days)
Cash Flow Peak outflow Oct 15–18 $1.36M supplier & sub draws; ensure $1.5M liquidity buffer; invoice clients on Oct 3 and Oct 24

Who wrote this content?

The Dojo Business Team

A team of financial experts, consultants, and writers
We're a team of finance experts, consultants, market analysts, and specialized writers dedicated to helping new entrepreneurs launch their businesses. We help you avoid costly mistakes by providing detailed business plans, accurate market studies, and reliable financial forecasts to maximize your chances of success from day one—especially in the construction market.

How we created this content 🔎📝

At Dojo Business, we know the construction market inside out—we track trends and market dynamics every single day. But we don't just rely on reports and analysis. We talk daily with local experts—entrepreneurs, investors, and key industry players. These direct conversations give us real insights into what's actually happening on jobsites.
To create this content, we started with our own conversations and observations. But we didn't stop there. To make sure our numbers and data are rock-solid, we also dug into reputable, recognized sources that you'll find listed at the bottom of this article.
You'll also see custom tables that capture and operationalize key requirements, making complex information easy to apply. We hope you find them helpful! All other illustrations were created in-house and added by hand.
If you think we missed something or could have gone deeper on certain points, let us know—we'll get back to you within 24 hours.

How many projects should be active this month?

Run five active projects to balance revenue with control in October 2025.

Project A (retail fit-out) and B (12-unit residential) drive most near-term revenue, while C (warehouse) and D (roadworks) add volume and equipment utilization; E (villa renovation) fills finishing crews between inspections.

Keep each job with a named PM, weekly look-ahead, and frozen two-week lock plan to prevent scope creep.

Freeze any sixth project until cash coverage is ≥1.2× the next 30-day outflows and critical crews are at ≤85% utilization.

Review portfolio load every Friday at 4:00 pm with PMs and QS for acceptance or deferral decisions.

What is the total budget this month and how is it split by project?

The October 2025 working budget is $4.85M across five projects with a 10% central contingency.

Allocate budgets strictly by WBS, linking each cost code to a schedule item so finance mirrors progress; keep vendor rates fixed by signed POs before mobilization.

Hold back 2% of each package for punch and defect correction; separate consumables from capitalizable assets for clean job costing.

Escalation clauses apply to steel and asphalt packages only, capped at 6% month-over-month.

Issue budget variance reports every Monday to flag >±3% deviations for immediate action.

Project October Budget (US$) Breakdown & Notes
A – Retail Fit-Out $650,000 Joinery $180k; MEP $210k; finishes $160k; PM/overheads $60k; 10% allowance for client changes signed off daily
B – 12-Unit Residential $1,800,000 Structural $620k; MEP rough-in $450k; façade $320k; interiors $300k; prelims $110k; retainage 5%
C – Warehouse Shell $1,600,000 Concrete/steel $930k; roofing $280k; drainage $140k; prelims $150k; testing & inspections $100k
D – Roadworks (2.1 km) $600,000 Sub-base $140k; asphalt $330k; traffic management $60k; plant & fuel $70k; night work premium included
E – Villa Renovation $200,000 Demolition $30k; structural alterations $60k; finishes $70k; MEP upgrades $30k; permits & fees $10k
Central Contingency $0.45M (10%) Released by GM on written justification; unused contingency returns to margin at month-end
Total $4,850,000 Budgets align with two-week look-ahead; all POs tied to cost codes; daily cost capture in field app

What materials are required and when must they arrive?

Materials must land just-in-time by phase to cut storage risk and theft.

Concrete, steel, CMU, asphalt, drywall, and key MEP items anchor this month’s schedule; long-lead items (glazing, HVAC AHUs) require confirmed ETAs before related works start.

All deliveries need gate slots and lift plans; partial shipments are acceptable if they unlock critical path tasks.

QA/QC checks (mill certs, slump tests, moisture content) must be recorded at receipt.

Any late delivery over 24 hours triggers resequencing to protect the critical path.

Material Quantity (Oct) Delivery Window & Project Use
Ready-mix Concrete 1,720 m³ Week 1–3; B/C slabs & footings; slump 100–120 mm; cube tests 7/28 days logged
Reinforcing Steel 165 t Week 1–2; B/C mats & beams; heat numbers tracked; bending schedule pre-approved
CMU Blocks 42,000 units Week 2; A/B partitioning; store on pallets under cover; mortar strength M10
Asphalt 1,150 t Week 3; D paving nights; plant 22 km away; compaction targets ≥95% Marshall
Drywall & Framing 7,500 m² Week 3–4; A/B interiors; moisture-safe storage; fire-rated boards where specified
Electrical Cable 38 km Week 2–4; A/B/C; pull by zone; megger tests ≥1 MΩ; label both ends
HVAC Equipment 5 AHUs + 42 FCUs Week 4; A/B; pre-start checklists; commissioning plan signed before energization

What workforce do we need by trade?

Plan for an average of 118 workers on site per day across all projects.

Peaks occur during B and C slab cycles; night crews are reserved for D paving; HSE coverage remains at a minimum of 1 officer per two jobsites.

Keep absenteeism buffer at 8% via vetted floaters; enforce tool-box talks daily at 7:30 am.

Any trade below 75% planned headcount for two days triggers reallocation from non-critical tasks.

Approve overtime only when it protects a critical path task documented in the look-ahead.

Trade / Role Avg. Headcount Deployment & Notes
Carpenters & Formwork 34 Focus on B/C slabs (Wk 1–3); rotate to A for fit-out frames
Masons / Block Layers 26 CMU walls in A/B (Wk 2–3); maintain QA for plumb and bond
Steel Fixers 14 Rebar cages for footings & beams (B/C); prefab where possible
Electricians 12 MEP rough-in A/B/C; inspection checklists per zone
Plumbers 10 Risers and drainage B; roof drainage C; pressure tests logged
Equipment Operators 8 Excavators & paver at D; crane at C; cross-licensed staff
HSE Officers 3 Daily audits; close out NCRs within 48 hours; induction tracking

You’ll find detailed workforce planning benchmarks in our construction company business plan, updated every quarter.

Which subcontractors are needed and what is their status?

Twelve subcontractors are engaged this month: nine confirmed, three pending award.

Pending awards are asphalt paving (D), glazing (B), and HVAC (C); each must be let by October 6 to preserve downstream activities.

All subs must submit RAMS, insurance, manpower histograms, and delivery programs before site access.

Unrecovered defects older than 7 days suspend further progress payments until rectified.

Back-to-back warranties and liquidated damages mirror client contracts to protect margins.

What heavy machinery is required and for how long?

Seven key units are scheduled with precise day counts and site allocations.

Conflicts are resolved by a shared plant calendar; fueling and maintenance windows are booked off-hours; operators are cross-trained to reduce idle time.

Hire rates are locked weekly; any idle over 2 hours/day is reported to the plant manager for redeployment.

Lifting plans and ground bearing checks are mandatory before crane operations.

Equipment movements are consolidated to cut low-boy transport costs by 18–22% this month.

Equipment Days (Oct) Primary Tasks & Site
50-t Mobile Crane 12 C: steel erection & roof trusses; certified rigger on shift
Excavator (20 t) – 2 units 10 total D: trenching, sub-base trimming; fuel bowser shared
Asphalt Paver 4 (nights) D: wearing course; QC density tests per 250 m
Concrete Pumps – 3 units 9 B/C slab pours; backup boom on standby for >800 m³ days
Telehandler 8 A: material handling; lift plan and spotter assigned
Roller (12 t) 6 D: compaction to ≥95% Marshall; daily calibration checks
Generators (100–200 kVA) 20 A/B/C temporary power; weekly load bank tests
business plan building contractor

What safety and compliance inspections are scheduled and how do we prepare?

Plan three internal audits and two external inspections this month across the five jobs.

Preparation includes toolbox talks, method statement briefings, PPE checks, scaffold tags, and equipment certificates; high-risk work (lifting, hot works, confined spaces) requires permits and spotters.

Close non-conformities within 48 hours and document corrective actions with photos in your field app.

Emergency drills are booked for October 10 (A/B) and October 22 (C/D) with attendance sheets.

HSE KPIs: TRIR = 0, near-miss reporting ≥5 per site per week, corrective action closure ≥95% on time.

What supply chain challenges do we expect and what are the contingencies?

  • Steel: possible mill backlog; lock bending schedules by Oct 3 and approve alternates of equivalent grade.
  • Asphalt: night-plant capacity constraints; secure priority slots and nominate a standby plant.
  • Glazing lead: customs clearance risk; pre-file documentation and split shipments by elevation.
  • HVAC: AHU/FCU electronics delays; keep 2 spare control modules and pre-commission ductwork.
  • Transport: fuel price spikes; combine loads and fix rates for the month with a surcharge cap.

This is one of the strategies explained in our construction company business plan.

What cash flow is required, including supplier and subcontractor payments?

Projected October cash outflow is $3.02M with a mid-month peak.

Supplier draws (materials) account for $1.74M, subcontractor progress claims for $1.13M, and plant/fuel/overheads for $0.15M; maintain a $1.5M liquidity buffer to avoid work stoppages.

Client invoices go out on October 3 (interim) and October 24 (second interim); expect average 18-day DSO with 5% retainage.

Early-pay discounts at 1.5% are applied to three strategic suppliers where cash allows.

Any negative variance >$250k triggers scope resequencing to late-cash items without damaging the critical path.

Cash Item Amount (US$) Timing & Notes
Materials (Concrete, Steel, Asphalt, MEP) $1,740,000 50% on delivery, 50% net-14; cube/QA passed before release
Subcontractors (MEP, Glazing, Paving, Interiors) $1,130,000 Monthly progress; retainage 5%; pay within 7 days of client cert
Plant Hire & Fuel $90,000 Weekly; idle time deductions enforced
Testing & Inspections $25,000 Per test schedule; no pay without signed reports
Permits & Fees $12,000 As billed; ensure receipt before activity starts
Overheads (PM, HSE, Site Ops) $23,000 Payroll on 15th & 30th; GL codes separate per project
Total Outflows $3,020,000 Liquidity buffer ≥$1.5M maintained throughout the month

What critical milestones must be achieved this month?

Hit five contractual milestones to keep revenue certificates on track.

B: Level 3 slab pour by Oct 12; C: steel erection 60% by Oct 19; D: wearing course complete by Oct 28; A: MEP rough-in inspection passed by Oct 21; E: interiors 50% by Oct 25.

Each milestone has a pre-list of prerequisites; PMs must sign readiness checklists 48 hours before the planned date.

Slippage beyond 48 hours must be escalated to the GM with a resequencing plan and resource moves.

Daily “traffic-light” dashboard shows status and blockers for immediate action.

Milestone Target Date Prerequisites & Evidence
B – Level 3 Slab Poured Oct 12 Rebar inspect signed; formwork check; pump & backup confirmed; cube tests logged
C – Steel Erection 60% Oct 19 Anchor bolts verified; lifting plan; weather window ≥6 hrs
D – Wearing Course Complete Oct 28 Sub-base tests ≥98% CBR; plant slot confirmed; traffic plan approved
A – MEP Rough-in Passed Oct 21 IR tests; pressure tests; inspection request submitted 48 hrs prior
E – Interiors 50% Complete Oct 25 Joinery shop drawings approved; material on site; QA hold points set
Portfolio – HSE Drill Oct 22 Attendance sheets; debrief minutes; corrective actions assigned
Portfolio – Client Billing Oct 24 Daily diaries signed; photos; progress certs; invoice pack issued
business plan construction company

What reporting or documentation is due this month?

  • Weekly progress reports (photos, S-curve, earned value, delays/claims log) every Friday 5:00 pm.
  • HSE packs (induction logs, PTWs, inspections, near-misses) every Tuesday 10:00 am.
  • Quality dossiers (ITPs, checklists, test results) uploaded within 24 hours of activity.
  • Commercial reports (cost-to-complete, committed vs. budget, cash forecast) every Monday noon.
  • Client billing submissions with sign-offs by Oct 24 close of business.

We cover this exact topic in the construction company business plan.

What risks could impact delivery and how will we mitigate them?

  • Weather windows: keep rain calendars; shift pours/paving to earliest clear slots.
  • Material delays: approve alternates; split deliveries; resequence non-critical tasks.
  • Labor gaps: keep an 8% floater pool; cross-train; activate standby subcontractors.
  • Design changes: enforce change control; price and approve before fieldwork starts.
  • HSE incidents: mandatory permits; spotters; stop-work authority for all staff.

Get expert guidance and actionable steps inside our construction company business plan.

business plan construction company

Conclusion

This article is for informational purposes only and should not be considered financial advice. Readers are encouraged to consult with a qualified professional before making any investment decisions. We accept no liability for any actions taken based on the information provided.

Sources

  1. BCI Central – Thailand Construction Leads
  2. U.S. Census – Construction Spending
  3. OpenText – Budget Planning
  4. Smartsheet – Project Budget Templates
  5. ARS Contracting – Material Delivery Optimization
  6. StruxHub – Delivery Scheduling
  7. Rdash – Construction Supply Chain 2025
  8. Yaveon – Material Requirements Planning
  9. Construction Coverage – Spending Data
  10. Autodesk – Construction Statistics
Back to blog

Read More

The business plan to start a construction company
All the tips and strategies you need to start your business!
What startup budget to start a construction company?
How much do you need to start? What are the main expenses? Can we do it without money?
The financial margins of a construction company
How much profit can you reasonably expect? Let's find out.